Ellis County Hwy CR                                                    Oak Leaf, Texas                       

Replace bridge.  160 LF 30" drill shaft, 142 LF RC pipe, 310 CY rip rap, rock filter dams, vegetative watering, driveways, excavation and drill seeding. 

cache/wst.opf.4791212.xml

Potter County Hwy CR                                                            Amarillo, Texas               

Replace bridge and approaches.  599 CY excavation, 124 CY embankment, 689 LF drill shaft, retaining wall, gabion mattresses, rock filter dams.



Randall PR  5 Palo Duro Canyon-Phase 2                                Canyon,Texas            
                            
Replace concrete water crossings with 3 each 130' span bridges, 2,000 CY gabions, 1,880CY excavation, 16,568 CY embankment, 3,892 SY erosion control compost, 283 SY soil retention, blankets, 1,293 LF 24" drill shaft, 42 CY rip rap, 792 LF rail.



Estelle Creek Weir Structure Replacement                                     Irving, Texas            


Removal of existing concrete weir structure, 24" reinforced concrete piers, structural concrete, gabion baskets, and gabion mattress, rock rip rap, and associated fill and grading for erosion repairs. 


President George Bush Turnpike (PGBT-WE),Segment 7 Mitigation at West Trinity River and Johnson Creek                                                         Dallas, Texas                      

80 CY embankment final, 929 CY block sodding, vegetative watering, 25 CY concrete flume, 65 CY,  rip rap stone common grout 6 inch, 255 CY rip rap, 24 inch biodegradable erosion control logs 12" diameter install and remove, 1192 SY blading work erosion and sediment control



Randall County HWY PR 5                                                  Canyon, Texas             

3 bridges, 16,000 CY embankment, 2,000 ft of new road, 1,300 ft. drill shaft, 7,100 ft. temporary MSE wall, 800 CY gabion.  
cache/wst.opf.4528781.xml

Construction of Cedar Creek and Richland Chamber Intake Access Bridges                                                                                                   Waxahachie, TX                                                               

Demolish the existing steel and cable bridges and wood decks, partially demolish the existing grated walkway at bridges to install the new bridge.  Construct a new pre-fabricated steel access bridge, install a new metal stair, demolish the existing overhead power line from the bridges, new electrical power, site paving, grading, and civil improvements.

cache/wst.opf.4694931.xml

TRWD-Henderson Co. ITB #14-113; T75 and X51 Valve Replacements                 Waxahachie, Texas         

Replace valves and install fiberglass manhole and aluminum hatch.




Golfer's Way Culvert Rehabilitation                                                               Azle, Texas            

Slip lining an existing 2-barrel, 8' diameter culvert with HDPE, concrete aprons, rock rip rap, and associated work.




2014 Wichita River Flood Control Clearing                                   Wichita Falls, Texas              

Tree and vegetation removal along the Wichita River


Matthews Interceptor Drainage Improvements                       Richland Hills, Texas       

800 ft 8'x8' box culvert, 1,300 ft 6'x6' box culvert, 1,200 ft 6"-36" sewer/water, 1,000 lot new road, curb and gutter, 1,500 CY 36" rip-rap




TxDOT Wise Hwy FM 51                                                                               Decatur, Texas            

Drainage structures and embankments,
Rip Rap, (3) Culvert Boxes, and (2) Wingwalls

 

Walnut Creek Utility Stabilization                                                              Mansfield, Texas             

200 ft 42" sewer, 2 junction boxes, 10 drill shafts, sewer by pass, 7,100 ft redi-rock wall, 1,500 CY of excavation



Cedar Creek Spillway Improvements                                                        Trinidad, Texas          

Installation of 2 170ft drainage channels, 4 piezometers, 1000CY grouted rip rap 

 

Mass Grading and Related Construction for Hebron 121                              Lewisville,Texas        

 192,000 CY of embankments

Sanitary Sewer Easement Clearing & Gate                                     Denton, Texas       

79,000 LF 16’ easement clearing, 10,900 LF 26’ easement clearing, install 100 gate

 

Roy Reynolds Bridge Abutment                                                 Harker Heights, Texas      

250 LF Sheet Piling, 250 LF Reinforced Concrete Sheet Piling Cap, Traffic Control


Shady Shores Erosion Repair                                                      Shady Shores, Texas        

Repair dam, pump down ponds, excavate pond/ fill slope, place soil cement, and test soil cement.



Country Lakes West Phase 1 Improvements                                           Argyle, Texas        
 

 80,000 CY of embankment

 

Grading for Villages Phase 1                                                                Arlington, Texas         

Clearing, grubbing, excavation, fill, pump, haul, seed


FM 709 Bridge Erosion Repair                                                             Corsicana, Texas       

Prepare 3 ac ROW, 48.6 cy concrete, Rip Rap & 1,244 cy, Gabions
 
cache/wst.opf.4196915.xml
Storm Sewer Water Detention System                                                     Laredo, Texas        

Preparing Row, Flowable Backfill, Riprap, Box Culvert, 24” RCP, Inlets, Manholes, Headwall, Traffic Handling, Driveways, Sediment Control
 
SH 6 Place Rip Rap for Scour Repair                                                    Navasota, Texas        

Prepare right‐of‐way, tree removal, excavation, seeding, watering, backfill, install riprap
 
cache/wst.opf.4019234.xml
Eagle Mountain Dam Upgrade                                                            Fort Worth, Texas         

Install 29 relief wells, along the slope of the dam, to be interconnected with piping and outfall systems at 7 locations ranging from 22’ to 67’ in depth, Remove and replace chain link fence, Construct 100 lf of max thickness of 4’ embankment, Provide and maintain traffic controls, Erosion control, and Clearing and grubbing

cache/wst.opf.4112710.xml
72" Water Transmission Phase 2                                                             Dallas, Texas          

Bank Stabilization along the Trinity River banks including furnishing and installing 2,600 CY of Gabion Baskets, with Gabion Mattress Structures, 3,901 LF of 30" Drill Shaft, 87 LF 72” RCCP Repair/Replace, 732 CY of Structural Concrete Beams, 198 Active Rock Anchors, 1,000 CY of Stabilized Backfill, 300 CY of Flowable Backfill, Dewatering, Replacing Paved Surfaces with Hot-Mix Asphalt Pavement

cache/wst.opf.4112636.xml
Mountain Creek Watershed Site #9 FRS                                            Midlothian, Texas          

Repair both the downstream and upstream slopes of the existing principal spillway and 100 foot auxiliary spillway of the floodwater detention dam structure that is 1,800 feet long and 34 feet high by excavating and rebuilding the slopes with compacted lime-treated earthfill and constructing an impact basin, including clearing and grubbing; stripping the lime processing area and the embankment; constructing jobsite access; processing soils with lime; excavating and placing earthfill on the wave berm; placing lime-treated earthfill on the embankment; stripping and excavating of borrow areas; grading, shaping and replacing topsoil; requiring 26,000 CY excavation; 1,000 tons of lime; 17,000 CY of lime-treated earthfill; 29,000 SY of topsoil; 250 tons of riprap; 2,000 FT of sediment filters; 2,800 LF of barb wire fence and 17 AC vegetation
    
cache/wst.opf.2349519.xml
72" Water Transmission Phase 1                                                               Dallas, Texas          
10,000 CY of Gabion Baskets, 6,300 LF of 30” Drill Shaft, 72” RCCP Repair/Replace, 5 acre Clearing, 1,500 tons Grouted Rip-Rap, 1,000 CY Structural Concrete Beams, 23,000 LF of Active Rock Anchors, 3,500 SF of Sheet Piling, 1,000 LF Riverside Cofferdam/Dewatering
   
cache/wst.opf.2433807.xml
Highland Oak Crossing Channel Improvements                                      Keller, Texas          

1,800 CY Gabions in Pond, 1,500 CY Gabions in Channel, Wetland Plantings, 18,000 CY Excavation and Haul Out, Stream Water By-pass, 20,000 SY Seeding.

cache/wst.opf.2565884.xml
West Denton Substation                                                                          Denton, Texas          

40,000 CY of excavation and haul off, tree removal, undercutting wet pockets and replace with suitable soil, remove 580’ and install 890’ chain link fence, cut and fill, install 2,500 tons of 6” of compacted crushed rock over entire yard and transition new expansion into existing yard rock, Sod or hydro-mulch all exposed slopes, install 2,800 SF of sheet piling retaining wall, install 3,500 sf of ground grid and fence grounding, install drainage ditches and berms, install silt fences and ditch and catch basin filters.
cache/wst.opf.2565920.xml
North McKinney Lift Station                                                                 McKinney, Texas          

Pump Station, Wier Structure and Site Piping, Special Features Include: 50 Feet Deep Excavation with 35,000 CY of Excavated Material, 4,000 tons of 247A Foundation Stabilization, 29,000 SF of Special Shoring, Dewatering, 42 ft of Static Water, 2,600 CY of Structural Concrete, 12,000 SF of Concrete Paving, Misc. Sewer 6” to 48”, 3 Each Owner Furnished Pumps, Misc. Interior Piping, Odor Control, HVAC, Masonry and Electrical
  
cache/wst.opf.2564952.xml
Alice Creek                                                                                                  Dallas, Texas          

1 acre of Clearing, 1,000 ft of 5’ Chain Link Fence, 1,000 yds of Excavation, 296 Soil Nails,  176 CY Concrete Beam, 1,800 CY Gabions.

Cottonwood Hike and Bike Trail                                                                 Dallas, Texas         
  
54,000 SF 6” Concrete Paving, 26,000 SF Redi-Rock Retaining Wall, 6,000 SF Cast In Place Retaining Wall, 4,000 yds Excavation, 7,000 tons of Type D Embedment, Misc. RCP Pipe and Headwalls.
 
cache/wst.opf.2617687.xml
El Lago Lake Wall Repair                                                                           Dallas, Texas          
 
Remove & Replace Approximately 140 LF of Lake Retaining Wall
.

Eagle Mountain Balancing Reservoir                                       Eagle Mountain, Texas          

This project consisted of 220,000 CY excavation/embankment, 26,000 CY soil cement, 85,200 SY Geonet/Geomembrane Liner, 7,800 LF under drain system, construction of a 25’ deep inlet structure and a 37’ deep outlet structure both with 72” auto valves, 560 LF 84” cement lined steel pipe, 5,000 LF flex base road, 3,500 LF concrete encased electric duct bank, 5,000 LF chain link fence and 5 acres of seed/mulch.

Hutton Branch Stream Restoration                                                     Carrollton, Texas         

20,000 tons of Rip Rap, 2,300 CY Gabion Baskets, 80,000 CY of earth to move, 17 acres clearing, (3) pedestrian bridges, 85,000 SF of 6" concrete sidewalk, 2,500 LF of sewer, 10 acre wetland seeding, Stream water bypass, Low water structure


cache/wst.opf.2433854.xml

Lift Station #65                                                                                Wichita Falls, Texas         

2,000 LF of HDPE, 1 each Wetwell, Bypass Pump Sewer
 

cache/wst.opf.2565164.xml
Jasper Clearwell Water Treatment                                                 Wichita Falls, Texas        

Construction of 5 Million Gallon Water Storage Reservoir, Baffling of Existing Clearwell, Concrete Coating of Existing Structures, and Associated Work.

cache/wst.opf.2615837.xml

Plano Parks Erosion Control                                                                      Plano, Texas         

600 CY Gabions, Excavation/Fill in Stream, 1,000 tons Rip-Rap, 3,000 SF Trail Concrete.

Spur 97 Bear Creek CSJ # 0094-08-006                                                   Euless, Texas         

Drop Structure Concrete Repair, Rip-Rap Repair, Stream Diversion.

Midway Ground Storage Reservoir #1                                                 Lewisville, Texas        

2 MG G.S.T. Piping, 10’ Undercut, and Moisture Condition Backfill.
    